Compliance
2 Open1 Critical80% Lockdown85% CDM
Status:
TypeEventSiteInspectorSeverityStatusFollow Up
Persimmon Site Safety Inspection
Quarterly safety inspection by Persimmon H&S team
Garendon Park
Phase 3
Mark Thompson
Persimmon Homes
minor
open
17 Jan
Slip on muddy access route
Operative slipped on muddy pathway near Phase 2 entrance. No injury sustained.
Garendon Park
Phase 2
-
minor
resolved
Unsecured load on delivery vehicle
Delivery driver arrived with unsecured bricks. Could have fallen during unloading.
Coalville Gateway
Phase 1
-
major
In Progress
15 Jan
HSE Spot Check
Unannounced HSE inspector visit to site
Barrow upon Soar
Phase 1
J. Williams
HSE
observation
closed
PPE compliance check
Subcontractor operatives not wearing hi-vis vests
Garendon Park
Phase 5
-
minor
resolved